From contract documents to an actionable mobilisation plan

Contract Readiness reads a new maintenance contract, proposes the obligations that must be in place before work starts, and links each one to the clause it came from. A reviewer checks every suggestion, assigns an owner and proves completion with evidence.

No sign-up needed. Your changes stay in your own private sandbox for 48 hours.

Sample contract · §7.3 Traffic managementp. 6

The Contractor must submit a Traffic Management Plan to the Principal at least 10 Business Days before the Commencement Date for all works on or adjacent to a public road.

AI proposes an obligation, linked to its source
Submit Traffic Management Plan to the Principal
Permits & approvalsCriticalDue 10 business days before startEvidence: approved TMP
AcceptEditReject

Example with fictional data.

AI reads. People review. Teams act.

AI does the reading and drafting. People make the decisions. The plan, owners and evidence live in one place.

01

AI reads

AI goes through the contract and proposes each obligation with the exact clause, page and section it relies on.

02

People review

A reviewer accepts, edits, rejects or queries each suggestion. Nothing enters the plan on its own.

03

Teams act

Owners work their tasks, attach evidence and clear blockers. A manager verifies each item before it counts.

Four ways AI helps, each with a guardrail

Extract requirements

Proposes obligations from the contract, with workstream, owner role, due-date basis and the evidence needed.

Guardrail: every suggestion must quote a passage that really exists in the document.

Suggest asset-column mappings

Reads the headings of an asset register and suggests how they map to the contract's asset template.

Guardrail: AI never fills in serial numbers, locations or dates. Rule-based checks find the gaps.

Ask this contract

Answers questions like "What must be ready before the start date?" and links to the clauses and tasks it used.

Guardrail: it says when the information isn't there, and it can only propose changes.

Draft the readiness narrative

Writes a short summary for the readiness review from the same snapshot as the dashboard.

Guardrail: the numbers come from a fixed calculation, not from the AI.

Two sample contracts to explore

Both use fictional organisations, people and documents.

Water network maintenance

Wattle Creek Water: network maintenance

  • Six workstreams and 24 approved obligations
  • AI suggestions waiting for review, with source clauses
  • A 30-row asset register with deliberate data problems
Transport asset maintenance

Southern Corridor Roads: roadside technology

  • Roadside signs, cameras and signals
  • Mobilisation plan with owners and due dates
  • A smaller example for comparison

Readiness you can check

The readiness figure is a simple, visible calculation: verified obligations divided by all applicable, approved obligations.

Suggestions don't count until approved

Unreviewed AI suggestions sit outside the total and keep the contract from showing as ready.

Done means verified

A task waiting for verification isn't complete. Required evidence must be accepted first.

People make the final call

"Ready for commencement review" means ready for a manager's decision, not permission to start work.

Independent prototype by Ali Shehzad. Built with fictional organisations, people and documents. It isn't affiliated with, commissioned by or endorsed by any contractor or client. It isn't legal advice, a safety clearance or a guarantee that a contract can start.
© 2026 Ali Shehzad · Portfolio of prototypes and capabilitiesGet in touch